Hot-Spot Treatment Accelerates Closure and Reduces
Remediation Cost
Reduced Contaminant PlumeMass (After 22 Months)
Problem: -Plume length greater than 300 feet
-Contamination extended off-site on to two neighboring properties
-Groundwater pumping rates to control plume projected to be in excess of
100 gpm
Project Objective: Achieve cost effective
closure of off-site properties without restrictions
Solution: -Enhance natural attenuation using an oxygen
release material
-Reduce duration of monitoring
-Reduce cost and time
Results are shown below
Larger View
Larger View
Results: After 22 Months Source area Ethylbenzene
concentrations have been reduced by 100%. Source area Xylene
concentrations have been reduced by 100%. Total Ethylbenzene
mass has been reduced by 95%. Total Xylene mass has been reduced
by 96%. The site can be Closed with restrictions. No
off-site restrictions are necessary.
Total Installation Cost: $14,300